Project Management Consultant |
Navajeevan |
Contractor |
Chandragupta Construction |
Scope of work |
Construction of balance work of officers rest house at Shiradi for S.P.Ahamadnagar
G + 1 = 1320 sq.mt. |
Project Exp.Cost (Rs in lakh) |
62.04 |
Tendered Cost (Rs in lakh) |
63.94 |
Date of Completion of Project |
06/03/2014 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
6 |