09 Jul, 2025 | 09:54 PM IST
Construction of 30 Residential Quarters for S.P. Buldhana at Dhamangaon, Taluka Motala, Dist. Buldhana Including All Infrastructural Amenities
Status District Name Location
Ongoing BULDHANA BULDHANA
Unit Commander Address
SP Buldhana Dhamangaon, Buldhana
Architect Vastu Shilp, Buldhana
Project Management Consultant Vastu Shilp, Buldhana
Contractor M/S KRANTI CONSTRUCTION
Scope of work Type II - 28 Qtrs, Type III - 02 Qtrs
Built up Area ( in sqm) 2603.92
Work Order Date 28/06/2024
Project Exp.Cost (Rs in lakh)
Tendered Cost (Rs in lakh) 914.87
Date of Completion of Project
Status Remarks Work in progress
Present Status Work in progress
Period of completion (in month) 15