Construction of 196 quarters including all infrastructural amenities for C. P. Nagpur at Pachpaoli, Nagpur
Status District Name Location
Completed NAGPUR NAGPUR
Unit Commander Address
C. P. Nagpur Pachpaoli, Nagpur.
Architect Nitin Bhalerao, Pune
Project Management Consultant Nitin Bhalerao, Pune
Contractor Harsh Construction Pvt. Ltd.
Scope of work 2 bldgs of Type B (stilt +7) 112 qtrs 10020.57 sqm 1 Bldg of Type C (stilt+7) 84 qtrs 7506.99 sqm Multipurpose Hall (G+1) 1670.35 sqm Reading Hall (G+1) 216.63 sqm Total No of Qtrs = 196 Total BUA = 19414.54 sqm
Built up Area ( in sqm) 19414.54
Work Order Date 03/12/2016
Project Exp.Cost (Rs in lakh) 6635.19
Tendered Cost (Rs in lakh) 5840
Date of Completion of Project 18/06/2019
Status Remarks Work is completed and handed over
Present Status Work is completed and handed over
Period of completion (in month) 24