Construction of 50 Police Quarters for M.T. workshop at police line Takli, Nagpur.
Status District Name Location
Completed NAGPUR NAGPUR
Unit Commander Address
CP Nagpur. S.P. Nagpur (M.T.) office
Architect Kharpate Associates, Nagpur
Project Management Consultant Comfort Construction , Nagpur
Contractor KETI Construction (I) Ltd.
Scope of work Type I Qtr. - 28 Nos. Type II Qtr. - 16 Nos. Type III Qtr. - 4 Nos. Type IV Qtr. - 2 Nos. 50 Qtrs. 10 Buildings Total BUI: 3595.39
Built up Area ( in sqm) 3595.39
Work Order Date 11/04/2007
Project Exp.Cost (Rs in lakh) 585
Tendered Cost (Rs in lakh) 517.73
Date of Completion of Project 14/05/2010
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 12