Architect |
Nadkarni Mahajan Associates |
Project Management Consultant |
Atul Thombare Associates |
Scope of work |
Administrative Building for Spl. IGP (G+2)
Infrastructural amenities
i) Compound wall
ii) Security cabin
iii) Land scape work
iv) Roads
v) Underground R.C.C. water tank
vi) External electrifications
vii) Street lighting, 71 K. V. Substation & D. G. set |
Project Exp.Cost (Rs in lakh) |
509.02 |
Tendered Cost (Rs in lakh) |
333.00 |
Date of Completion of Project |
15/11/2011 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
9 |