Administrative Building for S.P. Parbhani.
Status District Name Location
Completed PARBHANI PARBHANI
Unit Commander Address
S. P. Parbhani Existing S.P. Office premise, Parbhani, Dist. Parbhani.
Architect Pawan Engineers Latur
Project Management Consultant Pawan Engineers Latur
Contractor Prakash Constrowell Pvt. Ltd,
Scope of work Administrative Building (G+2) for S. P. Office Security Guard cabin, Electrical and D. G. Room, Infrastructural work. i) Compound wall ii) W.B.M., B. T. Road iii) Parking Area Development and parking shed iv) C.D. work and road side curbing v) External water supply and Under ground water tank Rain water Harvesting
Built up Area ( in sqm) 4140.48
Work Order Date 01/12/2009
Project Exp.Cost (Rs in lakh) 582.11
Tendered Cost (Rs in lakh) 515.31
Date of Completion of Project 15/11/2011
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over