36 (416) Police Quarters at Alibaug, Dist. Raigad for S.P. Raigad.
Status District Name Location
Completed RAIGAD RAIGAD
Unit Commander Address
Superintendent of Police, Raigad. Survey No. 126, Alibag, Raigad.
Architect CNA Architects.
Project Management Consultant C.B. Joshi
Contractor K.K.Thorat
Scope of work 3 Residential bldg. having 36 Type II quarters Total BUI 3138.24 sqm
Built up Area ( in sqm) 3138.24
Work Order Date 25/08/2011
Project Exp.Cost (Rs in lakh) 781
Tendered Cost (Rs in lakh) 609.30
Date of Completion of Project 07/01/2013
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 15