Construction of 3 Coastal Police Station for Commissioner S.I.D. M.S. Mumbai at Kelva and Arnala Dist Palghar and Dabhol Dist Ratnagiri
Status District Name Location
Completed PALGHAR PALGHAR
Unit Commander Address
SP Palghar / Ratnagiri Kelva, Arnala Dist Palghar. Dabhol dist Ratnagiri
Architect Liladhar Parab
Project Management Consultant Liladhar Parab
Contractor Shri Ganesh Construction
Scope of work Police Station at Kelva, Arnala Dist Palghar. Dabhol dist Ratnagiri
Built up Area ( in sqm) 816.08
Work Order Date 31/03/2016
Project Exp.Cost (Rs in lakh) 400.94
Tendered Cost (Rs in lakh) 303
Date of Completion of Project 18/05/2017
Status Remarks Work completed and Handed Over
Present Status Work completed and Handed Over
Period of completion (in month) 9