137(185) quarters at Karad, Satara
Status District Name Location
Completed SATARA SATARA
Unit Commander Address
S.P. Satara Karad, Satara
Architect B.G.Shirke Const. Tech.Pvt.Ltd.
Project Management Consultant B.G.Shirke Const. Tech.Pvt.Ltd.
Contractor B.G.Shirke Const. Tech.Pvt.Ltd.
Scope of work 137 quarters with all infrastructure Type II : 132 qtrs Type III : 4 qtrs Type IV : 01 Qtr Total BUI : 9479.42 Sqm
Built up Area ( in sqm) 9479.42
Work Order Date 06/03/2013
Project Exp.Cost (Rs in lakh) 2214
Tendered Cost (Rs in lakh) 1721.35
Date of Completion of Project 07/07/2014
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 18