Architect |
Samyak C2 infra Pvt. Ltd., Pune |
Project Management Consultant |
Atul Thombare Associates |
Contractor |
Prakash Constrowell Pvt. Ltd, |
Scope of work |
1) Type II Quarters 68 Nos
2) Type III Quarters 2 Nos
3) Type IV Quarter 1 Nos
--------
Total 71 Nos
4) Gymnasium
5) Multipurpose Hall |
Project Exp.Cost (Rs in lakh) |
1243 |
Tendered Cost (Rs in lakh) |
1199.00 |
Date of Completion of Project |
20/07/2011 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
12 |