3 Classrooms, Mess, WPTS, Solapur
  • Location not found for Kegaon - Hiraj
Status District Name Location
Completed SOLAPUR SOLAPUR
Unit Commander Address
Principal, WPTS, Solapur. Hiraj - Kegaon, WPTS, Solapur, Dist. Sangli.
Architect Ashok Pawar, Solapur
Project Management Consultant Structon Project Consultant, Solapur
Contractor Poorvi Enterprises, Mumbai
Scope of work 210 Hostel Principal quarter Parade Ground
Built up Area ( in sqm) 3213.18
Work Order Date 11/10/2006
Project Exp.Cost (Rs in lakh) 413
Tendered Cost (Rs in lakh) 318.74
Date of Completion of Project 31/12/2008
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 9