Head Quarter and Training Centre for Force One at Goregaon (E), Mumbai Phase I.
Status District Name Location
Completed MUMBAI MUMBAI
Unit Commander Address
Force One, Goregaon C.T.S. No. 14 B and 14 C, C.T.S. No. 258.
Architect Chaugule Patil Consultants Pvt.Ltd
Project Management Consultant Shashank Mehendale
Contractor Kamal Enterprises
Scope of work 1) Administrative & Bachlor''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''s Hostel Building - 1 No. (First + 3) 2) Type II Quarters - 3 Nos. (Ground + 3) and 1 No. (Ground + 4) 3) Type III (G+6) - 1 No. (Ground + 6) 4) Entrance Plaza with Gate - 1 no. (Ground +1) Total - 7 No. 1) Administrative & Bachlor''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''''s Hostel Building - 1 No. (First + 5) 2) Type II Quarters - 4 Nos. (Stilt + 7) 3) Type III (G+6) - 1 No. (Stilt + 7) 4) Entrance Plaza with Gate - 1 no. (Ground +1) Total - 7 No.
Built up Area ( in sqm) 19870.60
Work Order Date 12/07/2011
Project Exp.Cost (Rs in lakh) 6854
Tendered Cost (Rs in lakh) 6256.18
Date of Completion of Project 10/06/2016
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 24