Construction of Type III 3 Nos Quarters including all infrastructure amenities for Adl DGP (Prison) Maharashtra State Pune at Gat No 160 Yerwada Jail Dist Pune
Status District Name Location
Completed PUNE PUNE
Unit Commander Address
SP Pune Rural Yerwada, Pune
Architect M/S D. O. Nikam
Project Management Consultant M/S D. O. Nikam
Contractor M/ Ankita Construction
Scope of work Construction of Type- III 3 Nos, Quarters including allinfrastructure amenities for Adl. DGP (Prison) Maharashtra State Pune at Gat No. 160, Yerwada Jail, Dist. – Pune
Built up Area ( in sqm) 315.41
Work Order Date 20/06/2019
Project Exp.Cost (Rs in lakh) 87.94
Tendered Cost (Rs in lakh) 86
Date of Completion of Project 25/09/2020
Status Remarks Work is completed and handed over
Present Status Work is completed and handed over
Period of completion (in month) 9 months