27 Apr, 2024 | 08:21 PM IST
Construction of Type II 448 quarters for C P Mumbai at Marol Andheri East Mumbai
Status District Name Location
Ongoing MUMBAI MUMBAI
Unit Commander Address
C.P. Mumbai Marol, Mumbai
Architect Skyline Architects
Project Management Consultant Skyline Architects
Contractor Generic Engineering Construction and Projects Ltd.
Scope of work Construction of Type II 448 quarters for C. P. Mumbai, at CTS No.4, C/1 to 3 at Marol, Andheri (East)Mumbai
Built up Area ( in sqm) 51131
Work Order Date 11/09/2019
Project Exp.Cost (Rs in lakh)
Tendered Cost (Rs in lakh) 18194.94
Date of Completion of Project
Status Remarks Work in Progress
Present Status Work in Progress
Period of completion (in month) 30