Architect |
Tongase & Patil Engineers (Regd). |
Project Management Consultant |
Tongase & Patil Engineers (Regd). |
Scope of work |
Residential quarters
Type II - 12 qtrs x 7 Bldg = 84 qtrs
Type IIA - 10 qtrs x 1 Bldg = 10 qtrs
Type III - 6 qtrs x 1 Bldg = 6 qtrs
Type IV - 1qtrs x 1 Bldg = 1 qtrs
= 101 qtrs & Site office
Including all Infrastructural amenities |
Project Exp.Cost (Rs in lakh) |
887.55 |
Tendered Cost (Rs in lakh) |
712.97 |
Date of Completion of Project |
25/02/2008 |
Present Status |
100% work is completed and Handed Over |
Period of completion (in month) |
18 |