01 May, 2024 | 11:36 PM IST
Balance work of Officers rest house for S.P. Ahmednagar at Shirdi, Dist. Ahmednagar
Status District Name Location
Completed AHMEDNAGAR AHMEDNAGAR
Unit Commander Address
Superintendent of Police, Ahmednagar Shirdi, Dist. Ahmednagar
Architect Navajeevan
Project Management Consultant Navajeevan
Contractor Chandragupta Construction
Scope of work Construction of balance work of officers rest house at Shiradi for S.P.Ahamadnagar G + 1 = 1320 sq.mt.
Built up Area ( in sqm) 1320.00
Work Order Date 23/08/2013
Project Exp.Cost (Rs in lakh) 62.04
Tendered Cost (Rs in lakh) 63.94
Date of Completion of Project 06/03/2014
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 6