56 quarters for C. P. Aurangabad.
Status District Name Location
Completed AURANGABAD AURANGABAD
Unit Commander Address
C. P. Aurangabad Aurangabad
Architect Designer People, Nashik
Project Management Consultant Chavan Patil, Aurangabad
Contractor Parikh Construction Pvt. Ltd.
Scope of work Type II, 56 residential quarters.
Built up Area ( in sqm) 5767.52
Work Order Date 26/04/2013
Project Exp.Cost (Rs in lakh) 1143
Tendered Cost (Rs in lakh) 1013.47
Date of Completion of Project 25/10/2014
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 18