Construction of Administrative Building of Police Station and 24 Quarters for S.P. Chandrapur at Ballarpur Dist. Chandrapur Including all Infrastructural Amenities.
Status District Name Location
Completed CHANDRAPUR CHANDRAPUR
Unit Commander Address
S.P. Chandrapur Ballarpur, Chandrapur
Architect Vastu Shilp, Buldhana
Project Management Consultant Vastu Shilp, Buldhana
Contractor M/S R. Z. Malpani
Scope of work Type II – 1B (Stilt + 4) – 16 qtrs. Type III – 1B (Stilt + 2) – 8 qtrs. ------------- 24 qtrs. Police Station (G + 1) Site office (Gr.) Total BUA – 3281.00 sq. mt.
Built up Area ( in sqm) 3281.00
Work Order Date 22/09/2016
Project Exp.Cost (Rs in lakh) 1042.72
Tendered Cost (Rs in lakh) 898
Date of Completion of Project 20/09/2018
Status Remarks Work is completed and handed over
Present Status Work is completed and handed over
Period of completion (in month) 12