30 Apr, 2024 | 05:01 PM IST
100 Quarters at Dhule for S.R.P.F Gr.VI
Status District Name Location
Completed DHULE DHULE
Unit Commander Address
Commandant, SRPF Gr. 6, Dhule Dhule
Architect PHC Engineer
Project Management Consultant PHC Engineer
Contractor D.R. Patil & Co.
Scope of work Type II - 100 qtrs
Built up Area ( in sqm) 2055
Work Order Date 03/09/1993
Project Exp.Cost (Rs in lakh) 92.18
Tendered Cost (Rs in lakh) 92.18
Date of Completion of Project 31/12/1995
Status Remarks 100% work is completed and Handed Over
Present Status 100% work is completed and Handed Over
Period of completion (in month) 18